Incident 1746594 · SPDC · 7 Dec 2023
Upon excavation, it was observed that a previously repaired point had been tampered.The leak emanated from the previously installed ball valve.Some part of casted concrete around the repaired point was also destroyed by unknown person(s).
Continue through records connected by state or company. Similar records do not necessarily describe the same event.
10” Diebu Creek-Nun River Delivery Line Right of Way at Eniwari Yenagoa, Bayelsa State
18" Ebocha-Ogoda Pipeline @ Mgbede Community, ONELGA, Rivers State
12'' (km 15.5) OBAGI-RUMUEKPE CRUDE OIL EXPORT LINE @ OBIEMERENYI, AHOADA EAST L.G.A
10”0bob-Ebocha Pipeline at old Obrikom Flowstation, Omoku Community Onelga.
4" NKALE WELL 13 FLOWLINE@ODOGWA 1, NKALE ETCHE LGA.