Incident 2920756 · SPDC · 19 Apr 2021
A drilled hole of about 10(mm) at 3 O'clock position on the pipeline drilled by unknown persons at first incident point was observed. Another drilled hole of 5(mm) was observed at 68cm apart from first incident point at 1 O'clock position was observed at second incident point on the same facility.
12'' ENYIWEST -ENYIMAIN AT OGWU-IKPELE
4'' SARA DELIVERY LINE AT IDAMA JOKKA COMMUNITY R/S.
10” Diebu Creek-Nun River Delivery Line Right of Way at Eniwari Yenagoa, Bayelsa State
18" Ebocha-Ogoda Pipeline @ Mgbede Community, ONELGA, Rivers State
12'' (km 15.5) OBAGI-RUMUEKPE CRUDE OIL EXPORT LINE @ OBIEMERENYI, AHOADA EAST L.G.A