Incident 2664212 · SPDC · 12 Jun 2020
ONE SIDE OF THE CLAMP INSTALLED BY SPDC AFTER A PREVIOUSLY REPAIRED POINT WAS TAMPERED WITH BY UNKNOWN PERSONS. THERE WAS EVIDENCE TO PROVE THAT IT WAS TAMPERED WITH BECAUSE THE BOLT AND NUTS ON THE CLAMP WAS LOOSE DURING THE INVESTIGATION. ALSO, WHEN THE CLAMP WAS BROUGHT DOWN, FURTHER INVESTIGATION SHOWED THAT THER WAS AN EXTERNAL DENT ON THE CLAMP.
Open official source file
Continue through records connected by state or company. Similar records do not necessarily describe the same event.
10” Diebu Creek-Nun River Delivery Line Right of Way at Eniwari Yenagoa, Bayelsa State
18" Ebocha-Ogoda Pipeline @ Mgbede Community, ONELGA, Rivers State
12'' (km 15.5) OBAGI-RUMUEKPE CRUDE OIL EXPORT LINE @ OBIEMERENYI, AHOADA EAST L.G.A
10”0bob-Ebocha Pipeline at old Obrikom Flowstation, Omoku Community Onelga.
4" NKALE WELL 13 FLOWLINE@ODOGWA 1, NKALE ETCHE LGA.