Incident 2018/LAR/020/033 · NAOC · 19 Feb 2018
12MM DRILLED HOLE OBSERVED AT 6'O CLOCK POSITION ON THE 4" FLOW LINE
Continue through records connected by state or company. Similar records do not necessarily describe the same event.
11 WELLHEAD MANIFOLD AT OKPAI COMMUNITY
OKPAI 25S WELLHEAD AT BENEKU, NDOKWA EAST LGA
API Obama skimmer@Obamaflowstation in Nembe, Bayelsa state.
6'' Ogboinbiri Deep 5 Flowline at Ogboinbiri, Southern Ijaw LGA Bayelsa State.
24" AKRI - KWALE GAS PIPELINE AT BENEKU