Incident 2025 SAR/052/082 · OANDO · 4 May 2025
i.The incident point was covered by water and bubbles as at the time of initial investigation. ii.The surroundings were heavily impacted, the spill affected both the ROW and outside the ROW. iii.Upon excavation, the JIT observed that there was a tear of about 45cm at 6 o’clock position on the 14’’ pipeline. iv.An embankment was formed to contain the spill from flowing down the slope.
10” Diebu Creek-Nun River Delivery Line Right of Way at Eniwari Yenagoa, Bayelsa State
10”0bob-Ebocha Pipeline at old Obrikom Flowstation, Omoku Community Onelga.
Central Processing facility (CPF) at Nembe Crude Oil Export Terminal.
18" Obama/Brass Pipeline at Okoroma
4'' OBIAFU/OBOB 35s FLOWLINE at Otua community, Omoku in ONELGA, Rivers State.